Steelwork on site that Carillion hope to start putting up by the end of the week.
A small mobile crane is now in position at the top of the mountain that will be used in erecting the steelwork at the summit. The next phase will also focus on putting in the foundations for the service wing running alongside the platform and containing the Stationmasters Office. The pre-cast units for this section of the building are currently in the compound at Clogwyn Station.

Setting out using an EDM (Electronic Distance Measuring) instrument.
For the workmen it has meant some long days starting with catching the train up at seven in the morning and often not leaving the summit until six-thirty in the evening.

Phase 1 is virtually complete. The service wing will run eastwards (left).
Welcome to the Snowdonia-Active blog on the progress of redeveloping Snowdon's summit.