Phase One has been completed and while the numbered pieces of the steel framework are being carefully assembled, the foundations for the service wing are being dug out at the other end of the site.


Steel erectors putting together the frame of Hafod Eryri.


Digging-out to make space for the service wing.

Rock-netting is being installed to cover the steep back-wall of the site to prevent any loose rocks falling on to the workers below. The fine weather forecast for the week ahead will help ensure the good progress being made at the summit continues.


Celtest Ltd and Colin Jones (Rock Engineering) are responsible for stabilising
the back wall of the site with rock netting.