Installation of the final roof section on the main part of Hafod Eryri was completed ahead of schedule early this afternoon. This was despite being unable to fit any roofing for three days last week owing to high wind speeds: 22mph is the highest wind speed in which the crane is allowed to operate. The roof was expected to take two weeks to get in to place but took only five days. Thirty one sections of the Kalzip roofing system were fitted.


Hafod Eryri now with a roof.


Sterling Building have installed the Kalzip roofing.

The guttering still needs to be added and there is lots of work bolting the sections together to do. Stone slabs will also cover the roof to ensure it is sympathetic with the landscape. While the roof has been going on, digging out for the service-wing foundation units has continued.


Looking down and along the length of where the service-wing will be built.